Why was the lighthouse necessary?
• Some ten shipwrecks prior to 1890 along the Surf Coast
prompted authorities to plan the lighthouse .
Construction
• Construction started in late 1890 and the lighthouse
was illuminated in September 1891.
• The original tendered price for the lighthouse complete
with head lighthouse keeper's quarters, assistant's quarters,
stables and a store room was 8057 pounds, 18 shillings and
five pence. (About $20,000 today.)
|
 |
• The Chance Brothers (from Birmingham and the major manufacturers
in the world of lighthouse equipment of the day) manufactured the
First Order lantern and the 920mm focal radius lens in 1886. They
also manufactured the dome and the lighthouse equipment, including
the cast iron stairs and balustrades. These fittings remain in the
lighthouse today.
• Originally called Eagles Nest Point, it was renamed Split
Point in 1913. It is a cement-rendered concrete and crushed rock
tower, however the original drawings show that it was intended to
be constructed of stone. The contractors, Messrs. R. Anderson &
Sons (Anderson was a stonemason, originally from Scotland), had
great difficulty getting materials to the site. An effort was made
to transport materials by sea from Melbourne, but that route had
to be abandoned, as the vessel employed to carry the supplies was
wrecked through heavy weather on the coast. The stone was quarried
locally at Lookout Hill and the ironbark timber was obtained close
to the lighthouse.
• The tower design is modeled on that of a chimney as this
structure promotes air flow from the base to the top. This greater
air flow made the kerosene (and later, acetylene) flame shine brighter.
• The foundations are approximately 4 meters deep and are
built up solid with cement concrete. The walls at floor level are
approximately 2 meters thick, and finish about 50cm thick at the
top. About 800 meters of concrete was used.
• The centre pole and staircase formed the scaffold around
which the formwork was constructed and concrete poured. The men
stood on the wall to prepare the formwork for the higher sections.
The concrete and materials were then hauled up the sides and stairs.
• The tower is only painted on the outside so that moisture
can escape internally from the concrete to prevent concrete rot.
It was last painted in 2006.
> NEXT: The Lantern
|